CREXAuxiliaryMeasurements-Aug2020
From PREX Wiki
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
CREX Main << August 2020 CREX Run Plan
Schedule
- This plan is evolving as we move along
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Saturday Sept 12 | Owl | Production | DONE |
Day | Production | DONE | |
Swing (Zeke/Pitt) | Production | DONE | |
Sunday Sept 13 | Owl (Adam/Tao) | Production. | (No scans done.) 39 min ABU! |
Day (Bob/Eric) | Final Q2 measurement. Optics [1] | Acc mostly down; Bob took escorted access and switched to Counting Mode | |
Swing (Zeke/Pitt) | Optics [2] | Sanghwa for Analysis and remote assistance. Mostly completed optics. | |
Monday Sept 14 | Owl (Adam/Amali) | Inelastic spectrum. Poletip study [3] | Chandan for Analysis and remote assistance. Finished optics, inelastic spectrum, poletip study |
Day (Thia/Bob) | 10am - noon Beam studies 1: Hall in Controlled Access (CA) - Install blind At PMT, Blind main Detector; noon - 4:15pm Beam available to ready Halls - we take data with blinded tubes. | Devi required for tube blinding | |
Swing (Weibin/Eric, Devi on-call) | 4:15pm - 8:15pm Beam studies 2: Hall in CA - restore US PMTs, Compton e-Det work; 8:15pm - 9:15pm Beam recovery and onward delivery. Production. | ||
Tuesday Sept 15 | Owl (Adam/Amali) | Pedestal Scans, PITA scan. Production. | |
Day (Rom/Eric) | SAD Safety Meeting 9-11am https://primetime.bluejeans.com/a2m/live-event/tkcbphay ; Production if beam available | 7:45am South Linac down, cold box trip in CHL1, recovery 10.5 hours | |
Swing (Devi/Siyu) | Beam recovery and on to production on Ca-48. | ||
Wednesday Sept 16 | Owl (Bishnu/Victoria) | Production | |
Day (Simona/Eric/B.Yale - standby) | 8am start Moller measurement. Sign check. Followed by raster and Target study | Cameron supporting the raster study remotely and Bob locally. | |
Swing (Devi/?) | Complete raster and target study. Pedestal scans, PITA scan. Production | ||
Thursday Sept 17 | Owl (Victoria/Siyu) | Production. | |
Day (Rom/Weibin) | Production | ||
Swing (Zeke/Adam) | Production | ||
Friday Sept 18 | Owl (Victoria/Siyu) | 6am SHUTDOWN | |
Day (Rom/Weibin) | ----- |
Optics and Q2
- Q2 measurement (Done)
- Repeat of Q2 measurement, with improved pedestal noise control.
- Detector counting mode.
- S0 trigger
- production raster and beam position
- Optics Data (Done)
- Sieve IN, dp=+1, 0, (maybe -1). Raster/no raster thin C, raster H20
- Priority is 1 dp change (both arms!) plus backout, and 10 runs. Watercell runs should be long.
- Assume 3 hours for magnet changes and 2 hours for data taking. ~ 1 shift
- See grid on optics data spreadsheet
- Energy Measurement (Done)
- Doug did a parasitic energy measurement Sun, Sep 13 at 20:24 [4].
Backgrounds
- Blinded At PMTs (Done)
- Longish access to setup and back out, but short data taking period (production conditions).
- Reconfigure AT PMTs to use blinding cap, attach to US PMTs.
- This will be done during the long beam studies break on Monday
- software blinding on the AT PMTs must be disabled
- Check pedestal noise in counting and in integrating mode. We need low noise is the blinded tube, and we can't add noise to our main detector!
- Integrating measurement for asymmetry measurement
- (Do we want counting mode measurement for rate in blinded At tube?)
- (yield only normalizable using table-gain gain curves).
- Blinded Main detector? (Done)
- Need 2 hours to blind main detectors. Then another hour after meaurement to unblind.
- short-ish yield runs in integrating mode.
- Software blinding must be disabled on the blinded MD tubes for this study
- short counting mode run to get relative rate
- Then return. Keep AT blinded piggybacked for asymmetry measurement.
- Inelastic spectrum scan (Done)
- Needs a detailed run plan
- Counting mode. Current 0.5uA or so? Turn quartz HV off.
- Measure dp spectrum form dp=nominal to dp=-25%, in 5% steps. Use LHRS only.
- should scale all spectrometer magnets (including septum)
- Pole tip re-scattering (Done)
- Counting mode (VDC tracking). Counting mode on detector is ok (and helpful) but not needed.
- Q3 turned off.
- Run three septum setpoints: nominal, -5%, and +5%. Need ~1M S0 trigger events per run (and more is better).
Detectors
- Linearity Studies (PITA + current scans)
- These are ongoing - should continue regularly. At least once more,maybe twice.
- Useful to have one after we get the blinded tubes in place.
- Current scans for detector and BCM pedestals. Skip the BPMs, I think.
- Linearity LED tests
- This will be studied post run, during SAD
- detector crew were left off the SAD access list - Kent has repeated the request.
Other
- Sign check
- perform at next Moller polarimeter measurement
- run Moller, Compton, and parity DAQ for quick PITA scan
- Target/Raster study
- Set up for normal production mode. Call in experts (Bob M in person, Cameron remote).
- With each raster change we start with a brief C12 run for safety, then do a brief Ca48 run.
- Raster Scan Run Plan
Moller polarimetry
- One more measurement
Compton polarimetry
- Spectrum run
- Laser polarization changes
- linearity studies During SAD