== Daily Run Plan ==
 
  
Here are details of the daily run plan.  See also the [https://prex.jlab.org/wiki/index.php?title=RunPlan Global Run Plan].  The person responsible should ensure that
+
<br><br>
a crew of experts is available for the shift.  This schedule will be updated frequently by the Run Coordinator
+
[[Main_Page|<B>CREX Main</B>]] << [[Main_Page_PREXII|PREX II Main]] << [[Run Coordinator Tools]] <br><br>
as the situation on the ground changes.
+
 
<hr>
+
[[PREX2RunPlan2019 | PREX Global Run Plan]] -- [[RunPlanDaily_CREX|CREX Daily Run Plan]]
 +
 
 +
== Current Daily Run Plans ==
 +
 
 +
The current day is indicated by a color.
 +
 
 +
{| class="wikitable" border="1" style="width:100%; text-align:left;border-collapse:collapse"
 +
|-
 +
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
  
{| border="1"
 
|+ Daily Run Plan for PREX &nbsp; <font color="blue">(latest at bottom)</font>
 
! Date (2010) !! Shift !!---------- Activity (Responsible) ----------!!---&nbsp;Status&nbsp;---
 
|-
 
| 03/19
 
| Day
 
| pump down; Møller, Compton, septum install; Q2 repair<br />
 
Insert sieve. (Techs)
 
|done
 
|-
 
| 03/19
 
| Swing
 
| Beam restore (B-team)
 
| done
 
|-
 
| 03/20
 
| Owl
 
|
 
* Septum checkout (Michaels: Page when beam imminent & spectrometer ready)
 
also:
 
* Initial look at low current cavity monitors (Ahmed: Page when beam imminent & spectrometer ready)
 
* Target alignment (Michaels)
 
* VDC checkout (Michaels)
 
* Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
 
* GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)
 
| done
 
----
 
All at 1-2 µA.<br />
 
Scattered energy ~ beam energy = 1.063 GeV.<br />
 
Quad settings:
 
*Right arm:
 
** Q1: dI/dP= 411.2474 Amps/GeV/c
 
** Q2: dI/dP= 436.2014 Amps/GeV/c
 
** Q3: dI/dP= 433.3897 Amps/GeV/c
 
* Left Arm:
 
** Q1: dI/dP= 419.8772 Amps/GeV/c
 
** Q2: dI/dP= 435.6273 Amps/GeV/c
 
** Q3: dI/dP= 434.9682 Amps/GeV/c
 
"Usual" polarity
 
|-
 
| 03/20
 
| Day
 
| Beam off & hall open 9:00 am<br />
 
Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)
 
| done
 
|-
 
| 03/20
 
| Swing
 
|
 
* Close up hall
 
* Benesch tuning (1/2 - 2 hours)
 
* Verify quad polarities (Camsonne)
 
* Cavity monitors basic function test (Ahmed)
 
* Low current cavity monitors setup (Musson, Ahmed)
 
| done
 
 
|-
 
|-
| 3/21
+
| rowspan="3" | Wedsday, September 4
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Low current cavity monitors setup (Musson, Ahmed)
 
* Access for GEM installation (Camsonne)
 
| done but GEMs not ready
 
 
|-
 
|-
| 3/21
 
| Day
 
|
 
* Spectrometer checkout:
 
** Quartz detectors checkout (McNulty, Wexler)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** GEM checkout (Camsonne?)
 
* A line tuning (Benesch)
 
* Raster checkout
 
* Access:
 
** Low current cavities
 
** Target position
 
** Quartz
 
** Scintillator alignment
 
** LQ2
 
| done
 
|-
 
| 3/21
 
| Swing
 
|
 
* Low current cavity monitors setup (Michaels, Ahmed)
 
* Remove sieves
 
* Initial look at sieve out data
 
* Replace sieves
 
| done
 
|-
 
| 3/22
 
| Owl
 
|
 
* Pointing measurement (Riordan)
 
* Remove sieves
 
* Repeat pointing measurements with no sieves
 
* If done or unable to continue before 4 am page Luis Mercado to do lumi checks
 
* After 4 am page Dustin McNulty for detector work
 
|done
 
|-
 
| 3/22
 
 
| Day
 
| Day
 +
| Moller
 
|  
 
|  
* Optics (Liyanage) Sieve OUT.  NB Current limit 2 uA!
 
|done
 
 
|-
 
|-
| 3/22
 
 
| Swing
 
| Swing
 +
| Moller
 
|
 
|
* Optics continued, sieve IN.  NB Current limit 2 uA! (Shift Crew)
 
|done
 
 
|-
 
|-
| 3/23
+
| rowspan="3" | Thursday, September 5
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Quartz detectors resolution studies (KK, Dustin, John W)
 
* Lumi studies (Luis)
 
|done
 
 
|-
 
|-
| 3/23
 
 
| Day
 
| Day
 +
| Mott polarimetry measurements
 
|  
 
|  
* Remove water target. (Target, Techs)
 
* Reconfigure Moller cryo.
 
* '''Beam studies''' ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza)
 
|water cell removed, rest not finished
 
 
|-
 
|-
| 3/23
 
 
| Swing
 
| Swing
 +
| Production 71uA
 
|
 
|
* Target pumpdown
 
|done
 
 
|-
 
|-
| 3/24
+
| rowspan="3" | Friday, September 6
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Target pumpdown
 
|done
 
 
|-
 
|-
| 3/24
 
 
| Day
 
| Day
 +
| Production 85uA
 
|  
 
|  
* Target cooldown
 
|done
 
 
|-
 
|-
| 3/24
 
 
| Swing
 
| Swing
 +
| Production 85uA
 
|
 
|
* Tune high current beam into Hall A
 
|done
 
 
|-
 
|-
| 3/25
+
| rowspan="3" | Saturday, September 7
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
* Commission lead target, 50 uA (Bob)
 
* Lumis and oversampling tests (KK, Luis, Paul)
 
|in progress
 
 
|-
 
|-
| 3/25
 
 
| Day
 
| Day
 +
| Production 85uA
 
|  
 
|  
* Access to fix left dipole
 
|done
 
 
|-
 
|-
| 3/25
 
 
| Swing
 
| Swing
 +
| Production 85uA
 
|
 
|
* Parity Quality commissioning (Kent, Rupesh, Luis, Dustin)
 
* Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng)
 
|postponed
 
 
|-
 
|-
| 3/26
+
|-style="background: #FCF3CF;
 +
| rowspan="3" | Sunday, September 8
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
* High Luminosity Detector Commissioning
 
|in progress
 
 
|-
 
|-
| 3/26
 
 
| Day
 
| Day
 +
| Moller Polarimetry
 
|  
 
|  
*Moller Checkout
 
|postponed
 
 
|-
 
|-
| 3/26
 
 
| Swing
 
| Swing
|
+
| Q2 measurement and Spectrometer rescattering
*High Current on C12 (thick and thin)
+
| https://prex.jlab.org/wiki/index.php/RescatteringPlan
|partly done
+
 
|-
 
|-
| 3/27
+
| rowspan="3" | Monday, September 9
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
| no beam
 
 
|-
 
|-
| 3/27
 
 
| Day
 
| Day
|  
+
| SADness
| no beam
+
| Scheduled Accelerator Down begins
|-
+
|}
| 3/27
+
[[Run plan history | <B>Previous Daily Run Plans</B>]]
| Swing
+
|
+
*High-current on thick C12, adjust HV (Luis or Bob)
+
*Finish the commissioning of thick Pb target (Bob, Ahmed)
+
*Electronic Commissioning (KK, Luis, Paul, Jon et al)
+
|done, high-current tests continue
+
|-
+
| 3/28
+
| Owl
+
|
+
*Continue with the above, if necessary.
+
*High Luminosity Commissioning (Rupesh, Luis, Jon, Bob)
+
*BCM/BPM calibration (Rupesh)
+
*Establishing Parity Measurements, Charge feedback, blinding (Rupesh, Jon)
+
|not finished
+
|-
+
| 3/28
+
| Day
+
|
+
*Comparison Study of Optics Tunes (Seamus, Nilanga, Kiad)
+
*Sometime before Monday, submit the ATLIS plan for Dithering test (Rupesh)
+
|done
+
|-
+
| 3/28
+
| Swing
+
|
+
*Continue Optics if necessary.
+
*Continue High Luminosity Commissioning
+
|done
+
|-
+
| 3/29
+
| Owl
+
|
+
*Mini-production run (shift crew)
+
*Stop beam at 07:00 or whenever Ed Folts asks to.
+
|done
+
|-
+
| 3/29
+
| Day
+
|
+
*Open Hall A to set up Moller and Compton (Ed Folts, Sasha, Sirish, et.al.)
+
*Work on GEMs (Alex, Seamus, et.al.)
+
*MCC to do beam studies while Hall A open
+
*Detector linearity/LED tests (Luis)
+
*Setup WAC analysis (Mark, Mindy)
+
|done
+
|-
+
| 3/29
+
| Swing
+
|
+
*Moller magnet cooldown
+
*Optics and acceptance studies (Seamus, Ahmed, Nilanga)
+
|done
+
|-
+
| 3/30
+
| Owl
+
|
+
*Commission charge feedback (Mark)
+
*Current monitor calibration and pedestals determination (Mark)
+
*Quasi-production on Empty Target (owl shift crew)
+
|done
+
|-
+
| 3/30
+
| Day
+
|
+
*Access do work on Moller and Compton.
+
*Some GEM installation work. (Alex, Seamus, Kiad, Nilanga)
+
*Possible linearity/LED study. (Luis)
+
|done, except linearity
+
|-
+
| 3/30
+
| Swing
+
|
+
*First Commissioning of Moller -- Beam Checks (Sasha, Javier, Roman, Jay)
+
|done
+
|-
+
| 3/31
+
| Owl
+
|
+
*Scans of Septum and quad Q1 for tunes A and B. (Bob)
+
*Beam Studies of Helicity Correlations
+
|done
+
|-
+
| 3/31
+
| Day
+
|
+
*Beam Tuning (Jay Benesch)
+
|done
+
|-
+
| 3/31
+
| Swing
+
|
+
*Either or both of these:
+
* a) Moller Commissioning (Sasha, Javier, Roman, Jay)
+
* b) Tests of Dithering and other Beam-Related things (Kent, Rupesh)
+
|Moller was done
+
|-
+
| 4/1
+
| Owl
+
|
+
*If Kent's tests not done on Swing, continue here. (Kent, Rupesh)
+
*Beam and Septum scan with new tune (Seamus)
+
*Helicity-correlated beam studies (Shift crew)
+
|done
+
|-
+
| 4/1
+
| Day
+
|
+
* Beam Tuning (Jay)
+
|done, successful
+
|-
+
| 4/1
+
| Swing
+
|
+
* More beam tuning if necessary
+
* Moller Commissioning
+
|done
+
|-
+
| Friday 2 April
+
| Owl
+
|
+
*Assuming the HRS tune has been frozen
+
*Check detector alignment
+
*A_T studies
+
*Q<sup>2</sup> Measurements
+
|partly done, needs more work
+
|-
+
| Friday 2 April
+
| Day
+
|
+
*Tuning Beam for Compton
+
|done
+
|-
+
| Friday 2 April
+
| Swing
+
|
+
*  20:00 Obtain sieve runs (optics mini-run plan), Q<sup>2</sup> measurements (Bob)
+
|done, but not Q<sup>2</sup>
+
|-
+
| Saturday 3 April
+
| Owl
+
|
+
* Obtain sieve runs on Ta (Nilanga mini-run plan)
+
* Put in Lead target at low current and do counting-mode runs (Rupesh, Ahmed)
+
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
+
|done
+
|-
+
| Saturday 3 April
+
| Day
+
|
+
* Moller Commissioning <font color="green">(priority activity)</font>
+
* Work on getting into production mode (Mark, Rupesh)
+
|done, but not yet in prod.
+
|-
+
| Saturday 3 April
+
| Swing
+
|
+
* Moller commissioning
+
|done
+
|-
+
| Sunday 4 April
+
| Owl
+
|
+
* Counting data on tune Y (right arm) super-thin carbon
+
* Change to tune B
+
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
+
|done
+
|-
+
| Sunday 4 April
+
| Day
+
|
+
* Integrate-mode with thick carbon 50 uA
+
* Compton QWP1 calibration.
+
|done
+
|-
+
| Sunday 4 April
+
| Swing
+
|
+
* General Compton commissioning and pseudo-production (empty target) parity data at 50 uA.
+
|done
+
|-
+
| Monday 5 April
+
| Owl
+
|
+
* pseudo-production (empty target) parity data and Compton data at 50 uA.
+
|done
+
|-
+
| Monday 5 April
+
| Day
+
|
+
* 12:00 Jay to run optics test (~ 30 mins)
+
* Moller Spin Dance
+
* Set up vertical polarization and measure A_T
+
|done
+
|-
+
| Monday 5 April
+
| Swing
+
|
+
*Continue to setup up vertical polarization
+
*Measurements of A_T on Pb and C12
+
|done
+
|-
+
| Tuesday 6 April
+
| Owl
+
|
+
* Continue measurements of A_T on Pb and C12
+
|partly done
+
|-
+
| Tuesday 6 April
+
| Day
+
|
+
* Possible horizontal scan:  Tune B with sieve slit (Seamus)
+
* When ready: Relocate Quartz Detectors (Dustin, Jack)
+
|postponed: vacuum problems
+
|-
+
| Tuesday 6 April
+
| Swing
+
|
+
* In restricted access.
+
* Any activities that require access.
+
* Shift canceled
+
|
+
|-
+
| Wednesday 7 April
+
| Owl
+
|
+
* Shift cancelled
+
|
+
|-
+
| Wednesday 7 April
+
| Day
+
|
+
*Shift cancelled
+
* Investigate target vacuum problem
+
* Move quartz detectors (Dustin, Jack)
+
|Leak found at O-ring connection between target chamber and collimator box
+
|-
+
| Wednesday 7 April
+
| Swing
+
|
+
*Shift cancelled
+
|
+
|-
+
| Thursday 8 April
+
| Owl
+
|
+
*Shift cancelled
+
|
+
|-
+
| Thursday 8 April
+
| Day
+
|
+
*Shift cancelled
+
|Target chamber open, found that the 4th foil in Optics target blown off
+
|-
+
| Thursday 8 April
+
| Swing
+
|
+
*Shift cancelled
+
|
+
|-
+
| Friday 9 April
+
| Owl
+
|
+
*Shift cancelled
+
|
+
|-
+
| Friday 9 April
+
| Day
+
|
+
* To be determined.
+
* When ready: Install GEMs
+
|
+
|-
+
| Friday 9 April
+
| Swing
+
|
+
* Cancelled
+
|
+
|-
+
| Saturday 10 April
+
| Owl
+
|
+
* Cancelled
+
|
+
|-
+
| Saturday 10 April
+
| Day
+
|
+
* Cancelled
+
|
+
|-
+
| Saturday 10 April
+
| Swing
+
|
+
* Cancelled
+
|
+
|-
+
| Sunday 11 April
+
| Owl
+
|
+
* Cancelled
+
|
+
|-
+
| Sunday 11 April
+
| Day
+
|
+
* Cancelled
+
|
+
|-
+
| Sunday 11 April
+
| Swing
+
|
+
* Cancelled
+
|
+
|-
+
| Monday 12 April
+
| Owl
+
|
+
* Cancelled
+
|
+
|-
+
| Monday 12 April
+
| Day
+
|
+
* Cancelled
+
|
+
|-
+
| Monday 12 April
+
| Swing
+
|
+
* Cancelled
+
|
+
|-
+
| Tuesday 13 April
+
| Owl
+
|
+
* Cancelled
+
|
+
|-
+
| Tuesday 13 April
+
| Day
+
|
+
* Cancelled
+
|
+
|-
+
| Tuesday 13 April
+
| Swing
+
|
+
* Cancelled
+
|Tungsten collimator modified and installed.  Target pump down started and initially successful.
+
|-
+
| Wednesday 14 April
+
| Owl
+
|
+
* Cancelled
+
| Target pump down.
+
|-
+
| Wednesday 14 April
+
| Day
+
|
+
* Cancelled -- no shift workers (might need a TO)
+
* Target pump down and leak checking.
+
* When ready, begin target cooldown. (Dave Meekins and JP)
+
| Done.  Vacuum good.  Target cold.
+
|-
+
| Wednesday 14 April
+
| Swing
+
|
+
* Beam restore in Hall A
+
* Harp Scan - Shifters
+
* Raster size scan (goal is 3x3mm on empty cell) - Shifters.
+
* Detector Alignment - Dustin
+
* Dithering run with Septum On/Off - Rupesh.
+
|
+
|-
+
| Thursday 15 April
+
| Owl
+
|
+
<!--#* Beam restore in Hall A
+
#* When ready, begin <font color="blue">PREX recovery program:</font>
+
#* Check alignment of collimator.  Check temperature vs beam current. (Bob)
+
#* Check alignment of PREX quartz detector. (Dustin)
+
#* Check alignment of sieve slits, verify they did not change. (Seamus or Bob)
+
* Check alignment of Pb/diamond target and optimal raster size. (Bob)-->
+
* Thick Carbon Integrating Mode Run - Rupesh.
+
* Thick Carbon Dithering Run - Rupesh + Luis.
+
* Take Access: Change to counting mode and put sieve in - Ahmed.
+
|
+
|-
+
| Thursday 15 April
+
| Day
+
|
+
* Beam Studies -- establishing good beam in Hall A and Compton (Jay and B team)
+
|
+
|-
+
| Thursday 15 April
+
| Swing
+
|
+
* Detector Alignment - Dustin.
+
* Pb Alignment - Bob.
+
* Take access and put sieve in - Seamus.
+
* Sieve Alignment - Seamus.
+
* Take Access to remove sieve (Seamus) + switch to integrating mode (Jon) - '''Page Guy and Bob'''.
+
* Heat load test '''(run up to 500C)''' - Bob + Guy.
+
If possible, depending on heat load test:
+
* Relative Rate 12C/Pb Runs - Bob / Dustin.
+
* Start production (Rupesh, Luis, Kent, Krishna)
+
|
+
|-
+
| Friday 16 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Friday 16 April
+
| Day
+
|
+
* Production
+
|
+
|-
+
| Friday 16 April
+
| Swing
+
|
+
* Production @ 40uA
+
* Ramp up to 50uA (Guy + Bob)
+
|
+
|-
+
| Saturday 17 April
+
| Owl
+
|
+
* Production @ 50uA
+
|
+
|-
+
| Saturday 17 April
+
| Day
+
|
+
* Production @ 50uA
+
* Moller Checks + Measurement Starting 9am (Sasha)
+
|
+
|-
+
| Saturday 17 April
+
| Swing
+
|
+
* Moller till 7pm (Sasha).
+
* Compton (Jay Benesch + Megan).
+
* Production @ 50uA.
+
|
+
|-
+
| Sunday 18 April
+
| Owl
+
|
+
* Production @ 50uA
+
|
+
|-
+
| Sunday 18 April
+
| Day + Swing
+
|
+
* Production @ 50uA.
+
* Staring 3pm:
+
# Compton test (Jay Benesch + Megan).
+
# Page Dustin + Jon + Bob + Sasha.
+
# Q^2 Measurement (Bob)
+
# Call Compton Experts
+
# Access:
+
## Refill Moller Magnet.
+
## Check Compton HV.
+
## Remove S0.
+
## Go to counting mode (Dustin).
+
## Compton Stuff.
+
## Detector Mapping (Jon).
+
# Detector Alignment (Dustin).
+
# Q^2 Measurement (Bob).
+
# Relative Rate Measurement (Bob).
+
# Access to Return to Integrating Mode.
+
* Production @ 50uA
+
|-
+
| Monday 19 April
+
| Owl
+
|
+
* Production @ 50uA
+
|
+
|-
+
| Monday 19 April
+
| Day
+
|
+
* Production @ 50uA
+
|
+
|-
+
| Monday 19 April
+
| Swing
+
|
+
* Production
+
|
+
|-
+
| Tuesday 20 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Tuesday 20 April
+
| Day
+
|
+
* Production
+
* Beam studies from approx. 11 am to 2 pm
+
* Hall A Activities:
+
* -- Compton 1/4wave stepper (Abdurahim)
+
* -- Check R-HRS Q2 and switch to remote mode (Heidi)
+
* -- Adjust R-HRS A_T (Dustin)
+
* -- Take pedestal data (Jon)
+
* -- Check 4th GEM and possibly install 5th (Alex, Jon)
+
* -- Test motion of A_T detector R-HRS (Jon)
+
* -- Possible Compton shielding / HV check (Megan)
+
* -- Ramp Moller magnet, measure stray fields. (Sasha)
+
* -- Parasitic work on floor (Yi Qiang)
+
|
+
|-
+
| Tuesday 20 April
+
| Swing
+
|
+
* Tune up Compton
+
* Production
+
|
+
|-
+
  
| Wednesday 21 April
+
== Instructions for RC ==
| Owl
+
 
|
+
* Let the day shift know what to do while you attend the MCC meeting
* Production
+
* Copy the daily run plans for the previous week to the [[Run plan history]]
|
+
* Copy the [[Run Plan Template]] table to this page and change the dates
|-
+
* Update the plan above (if necessary) after the MCC meeting
| Wednesday 21 April
+
 
| Day
+
[[Category:HOW TO]] [[Category:SL]] [[Category:RC]]
|
+
 
* Production
+
<hr>
|
+
|-
+
| Wednesday 21 April
+
| Swing
+
|
+
* Production
+
|
+
|-
+
| Thursday 22 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Thursday 22 April
+
| Day
+
|
+
* Beam studies.  Transverse Phase Space Study in Wien.  (Reza, Mark, Rupesh)
+
* At ~2 pm start Moller commissioning
+
|
+
|-
+
| Thursday 22 April
+
| Swing
+
|
+
* Finish Moller (10 hours)
+
* Resume Production
+
* Don't forget the beam recovery procedure
+
|
+
|-
+
| Friday 23 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Friday 23 April
+
| Day
+
|
+
* Q<sup>2</sup> Studies (3 hrs) -- Dustin, Bob
+
* GEM studies are only parasitic.
+
|
+
|-
+
| Friday 23 April
+
| Swing
+
|
+
* Production
+
|
+
|-
+
| Saturday 24 April
+
| Owl
+
|
+
* Production on thick C12
+
|
+
|-
+
| Saturday 24 April
+
| Day
+
|
+
* Production on thick C12
+
* At about 2 pm switch to 120 Hz, still C12
+
* Run briefly on C12 at 120 Hz
+
* Switch to thick Pb target (120 Hz)
+
|
+
|-
+
| Saturday 24 April
+
| Swing
+
|
+
* Production on Pb at 120 Hz
+
|
+
|-
+
| Sunday 25 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Sunday 25 April
+
| Day
+
|
+
* Q<sup>2</sup> measurements - Bob, Dustin
+
* Otherwise production
+
|
+
|-
+
| Sunday 25 April
+
| Swing
+
|
+
* Production
+
|
+
|-
+
| Monday 26 April
+
| Owl
+
|
+
* Production
+
|
+
|-
+
| Monday 26 April
+
| Day
+
|
+
* Wien flip
+
|
+
|-
+
| Monday 26 April
+
| Swing
+
|
+
* Production
+
|
+
|}
+

Latest revision as of 16:22, 5 December 2019



CREX Main << PREX II Main << Run Coordinator Tools

PREX Global Run Plan -- CREX Daily Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Wedsday, September 4 Owl Production 71uA
Day Moller
Swing Moller
Thursday, September 5 Owl Production 71uA
Day Mott polarimetry measurements
Swing Production 71uA
Friday, September 6 Owl Production 71uA
Day Production 85uA
Swing Production 85uA
Saturday, September 7 Owl Production 85uA
Day Production 85uA
Swing Production 85uA
Sunday, September 8 Owl Production 85uA
Day Moller Polarimetry
Swing Q2 measurement and Spectrometer rescattering https://prex.jlab.org/wiki/index.php/RescatteringPlan
Monday, September 9 Owl Production 85uA
Day SADness Scheduled Accelerator Down begins

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting