Difference between revisions of "RunPlanDaily"

From PREX Wiki
Jump to: navigation, search
Line 26: Line 26:
 
|
 
|
 
|-
 
|-
|-style="background: #FCF3CF;
 
 
| rowspan="3" | Monday, July 15
 
| rowspan="3" | Monday, July 15
 
|Owl
 
|Owl
Line 32: Line 31:
 
| Except ~3 hour down time, we took good data
 
| Except ~3 hour down time, we took good data
 
|-
 
|-
|-style="background: #FCF3CF;
 
 
| Day
 
| Day
 
| FFB commissioning until 10AM. Take run with FFB (if ready) or w/o FFB (if not ready) until MOLLER experts walk in for MOLLER commissioning.  
 
| FFB commissioning until 10AM. Take run with FFB (if ready) or w/o FFB (if not ready) until MOLLER experts walk in for MOLLER commissioning.  
 
| MOLLER polarimeter commissioning is going on
 
| MOLLER polarimeter commissioning is going on
 
|-
 
|-
|-style="background: #FCF3CF;
 
 
| Swing
 
| Swing
 
|MOLLER commissioning
 
|MOLLER commissioning
Line 45: Line 42:
 
| rowspan="3" | Tuesday, July 16
 
| rowspan="3" | Tuesday, July 16
 
|Owl
 
|Owl
|   
+
|MOLLER Polarimeter and FFB commissioning    
 
|  
 
|  
 
|-
 
|-
 
|-style="background: #FCF3CF;
 
|-style="background: #FCF3CF;
 
| Day
 
| Day
|
+
| production after pass change
 
|  
 
|  
 
|-
 
|-

Revision as of 08:47, 16 July 2019

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Sunday, July 14 Owl Production+ analysis. FFB (30 min), BMW (30 min), Aq FFB tried, but didn't work.
Day Production+ analysis
Swing Production+ analysis
Monday, July 15 Owl Production+ analysis. Except ~3 hour down time, we took good data
Day FFB commissioning until 10AM. Take run with FFB (if ready) or w/o FFB (if not ready) until MOLLER experts walk in for MOLLER commissioning. MOLLER polarimeter commissioning is going on
Swing MOLLER commissioning
Tuesday, July 16 Owl MOLLER Polarimeter and FFB commissioning
Day production after pass change
Swing
Wednesday, July 17 Owl
Day
Swing

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting