Revision as of 13:42, 1 August 2019



PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Tuesday, July 30 Owl low current running beginning at 8am (if approved)
Day Target fix
Swing
  • Tests with no target
  1. collimator centering angles with tune beam
  2. BCM calibrations
  3. BPM calibrations
  4. position feedback study
Wednesday, July 31 Owl production at 70uA
Day
  1. HRS quad repairs
  2. target repairs
  3. Compton work
  4. BCM repair
  1. HRS quad repairs - both operational; nothing really done to right
  2. target repairs - mechanical work done, modifying software for new setpoints
  3. Compton work ongoing
  4. 2nd one working as well as we can tell
Swing
  1. Detector alignment (low current)
    • Main detectors
    • AT detectors
  2. production at 70uA
Thursday, August 1 Owl production at 70uA
Day production at 70uA
Swing Production running at 70uA
Friday, August 2 Owl Production running at 70uA
Day
  1. Wien flip starting at 8:30am
  2. Compton work in the hall: lens, mode-matching, PPLN tuning
  1. Possibly more Comtpn work in the hall
  2. Production running at 70uA
Saturday, August 3 Owl Production running at 70uA
Day
  1. Possible Chicane tuning by Yves (if laser ready)
  2. Production running at 70uA
Swing Production running at 70uA
Sunday, August 4 Owl Production running at 70uA
Day MOLLER starting at 8am
Swing Production running at 70uA
Monday, August 5 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA
Tuesday, August 6 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA
Wednesday, August 7 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting