Daily Run Plan for PREX (latest at bottom)
Date (2010) |
Shift |
---------- Activity (Responsible) ---------- |
--- Status ---
|
03/19
|
Day
|
pump down; Møller, Compton, septum install; Q2 repair
Insert sieve. (Techs)
|
done
|
03/19
|
Swing
|
Beam restore (B-team)
|
done
|
03/20
|
Owl
|
- Septum checkout (Michaels: Page when beam imminent & spectrometer ready)
also:
- Initial look at low current cavity monitors (Ahmed: Page when beam imminent & spectrometer ready)
- Target alignment (Michaels)
- VDC checkout (Michaels)
- Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
- GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)
|
done
All at 1-2 µA.
Scattered energy ~ beam energy = 1.063 GeV.
Quad settings:
- Right arm:
- Q1: dI/dP= 411.2474 Amps/GeV/c
- Q2: dI/dP= 436.2014 Amps/GeV/c
- Q3: dI/dP= 433.3897 Amps/GeV/c
- Left Arm:
- Q1: dI/dP= 419.8772 Amps/GeV/c
- Q2: dI/dP= 435.6273 Amps/GeV/c
- Q3: dI/dP= 434.9682 Amps/GeV/c
"Usual" polarity
|
03/20
|
Day
|
Beam off & hall open 9:00 am
Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)
|
done
|
03/20
|
Swing
|
- Close up hall
- Benesch tuning (1/2 - 2 hours)
- Verify quad polarities (Camsonne)
- Cavity monitors basic function test (Ahmed)
- Low current cavity monitors setup (Musson, Ahmed)
|
done
|
3/21
|
Owl
|
- Low current cavity monitors setup (Musson, Ahmed)
- Access for GEM installation (Camsonne)
|
done but GEMs not ready
|
3/21
|
Day
|
- Spectrometer checkout:
- Quartz detectors checkout (McNulty, Wexler)
- Lumi checkout (Mercado) (2 µA on Ta)
- GEM checkout (Camsonne?)
- A line tuning (Benesch)
- Raster checkout
- Access:
- Low current cavities
- Target position
- Quartz
- Scintillator alignment
- LQ2
|
done
|
3/21
|
Swing
|
- Low current cavity monitors setup (Michaels, Ahmed)
- Remove sieves
- Initial look at sieve out data
- Replace sieves
|
done
|
3/22
|
Owl
|
- Pointing measurement (Riordan)
- Remove sieves
- Repeat pointing measurements with no sieves
- If done or unable to continue before 4 am page Luis Mercado to do lumi checks
- After 4 am page Dustin McNulty for detector work
|
done
|
3/22
|
Day
|
- Optics (Liyanage) Sieve OUT. NB Current limit 2 uA!
|
done
|
3/22
|
Swing
|
- Optics continued, sieve IN. NB Current limit 2 uA! (Shift Crew)
|
done
|
3/23
|
Owl
|
- Quartz detectors resolution studies (KK, Dustin, John W)
- Lumi studies (Luis)
|
done
|
3/23
|
Day
|
- Remove water target. (Target, Techs)
- Reconfigure Moller cryo.
- Beam studies ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza)
|
water cell removed, rest not finished
|
3/23
|
Swing
|
|
done
|
3/24
|
Owl
|
|
done
|
3/24
|
Day
|
|
done
|
3/24
|
Swing
|
- Tune high current beam into Hall A
|
done
|
3/25
|
Owl
|
- Commission lead target, 50 uA (Bob)
- Lumis and oversampling tests (KK, Luis, Paul)
|
in progress
|
3/25
|
Day
|
- Access to fix left dipole
|
done
|
3/25
|
Swing
|
- Parity Quality commissioning (Kent, Rupesh, Luis, Dustin)
- Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng)
|
postponed
|
3/26
|
Owl
|
- High Luminosity Detector Commissioning
|
in progress
|
3/26
|
Day
|
|
postponed
|
3/26
|
Swing
|
- High Current on C12 (thick and thin)
|
partly done
|
3/27
|
Owl
|
|
no beam
|
3/27
|
Day
|
|
no beam
|
3/27
|
Swing
|
- High-current on thick C12, adjust HV (Luis or Bob)
- Finish the commissioning of thick Pb target (Bob, Ahmed)
- Electronic Commissioning (KK, Luis, Paul, Jon et al)
|
done, high-current tests continue
|
3/28
|
Owl
|
- Continue with the above, if necessary.
- High Luminosity Commissioning (Rupesh, Luis, Jon, Bob)
- BCM/BPM calibration (Rupesh)
- Establishing Parity Measurements, Charge feedback, blinding (Rupesh, Jon)
|
not finished
|
3/28
|
Day
|
- Comparison Study of Optics Tunes (Seamus, Nilanga, Kiad)
- Sometime before Monday, submit the ATLIS plan for Dithering test (Rupesh)
|
done
|
3/28
|
Swing
|
- Continue Optics if necessary.
- Continue High Luminosity Commissioning
|
done
|
3/29
|
Owl
|
- Mini-production run (shift crew)
- Stop beam at 07:00 or whenever Ed Folts asks to.
|
done
|
3/29
|
Day
|
- Open Hall A to set up Moller and Compton (Ed Folts, Sasha, Sirish, et.al.)
- Work on GEMs (Alex, Seamus, et.al.)
- MCC to do beam studies while Hall A open
- Detector linearity/LED tests (Luis)
- Setup WAC analysis (Mark, Mindy)
|
done
|
3/29
|
Swing
|
- Moller magnet cooldown
- Optics and acceptance studies (Seamus, Ahmed, Nilanga)
|
done
|
3/30
|
Owl
|
- Commission charge feedback (Mark)
- Current monitor calibration and pedestals determination (Mark)
- Quasi-production on Empty Target (owl shift crew)
|
done
|
3/30
|
Day
|
- Access do work on Moller and Compton.
- Some GEM installation work. (Alex, Seamus, Kiad, Nilanga)
- Possible linearity/LED study. (Luis)
|
done, except linearity
|
3/30
|
Swing
|
- First Commissioning of Moller -- Beam Checks (Sasha, Javier, Roman, Jay)
|
done
|
3/31
|
Owl
|
- Scans of Septum and quad Q1 for tunes A and B. (Bob)
- Beam Studies of Helicity Correlations
|
done
|
3/31
|
Day
|
- Beam Tuning (Jay Benesch)
|
done
|
3/31
|
Swing
|
- Either or both of these:
- a) Moller Commissioning (Sasha, Javier, Roman, Jay)
- b) Tests of Dithering and other Beam-Related things (Kent, Rupesh)
|
Moller was done
|
4/1
|
Owl
|
- If Kent's tests not done on Swing, continue here. (Kent, Rupesh)
- Beam and Septum scan with new tune (Seamus)
- Helicity-correlated beam studies (Shift crew)
|
done
|
4/1
|
Day
|
|
done, successful
|
4/1
|
Swing
|
- More beam tuning if necessary
- Moller Commissioning
|
done
|
Friday 2 April
|
Owl
|
- Assuming the HRS tune has been frozen
- Check detector alignment
- A_T studies
- Q2 Measurements
|
partly done, needs more work
|
Friday 2 April
|
Day
|
|
done
|
Friday 2 April
|
Swing
|
- 20:00 Obtain sieve runs (optics mini-run plan), Q2 measurements (Bob)
|
done, but not Q2
|
Saturday 3 April
|
Owl
|
- Obtain sieve runs on Ta (Nilanga mini-run plan)
- Put in Lead target at low current and do counting-mode runs (Rupesh, Ahmed)
- Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
|
done
|
Saturday 3 April
|
Day
|
- Moller Commissioning (priority activity)
- Work on getting into production mode (Mark, Rupesh)
|
done, but not yet in prod.
|
Saturday 3 April
|
Swing
|
|
done
|
Sunday 4 April
|
Owl
|
- Counting data on tune Y (right arm) super-thin carbon
- Change to tune B
- Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
|
done
|
Sunday 4 April
|
Day
|
- Integrate-mode with thick carbon 50 uA
- Compton QWP1 calibration.
|
done
|
Sunday 4 April
|
Swing
|
- General Compton commissioning and pseudo-production (empty target) parity data at 50 uA.
|
done
|
Monday 5 April
|
Owl
|
- pseudo-production (empty target) parity data and Compton data at 50 uA.
|
done
|
Monday 5 April
|
Day
|
- 12:00 Jay to run optics test (~ 30 mins)
- Moller Spin Dance
- Set up vertical polarization and measure A_T
|
done
|
Monday 5 April
|
Swing
|
- Continue to setup up vertical polarization
- Measurements of A_T on Pb and C12
|
done
|
Tuesday 6 April
|
Owl
|
- Continue measurements of A_T on Pb and C12
|
partly done
|
Tuesday 6 April
|
Day
|
- Possible horizontal scan: Tune B with sieve slit (Seamus)
- When ready: Relocate Quartz Detectors (Dustin, Jack)
|
postponed: vacuum problems
|
Tuesday 6 April
|
Swing
|
- In restricted access.
- Any activities that require access.
- Shift canceled
|
|
Wednesday 7 April
|
Owl
|
|
|
Wednesday 7 April
|
Day
|
- Shift cancelled
- Investigate target vacuum problem
- Move quartz detectors (Dustin, Jack)
|
Leak found at O-ring connection between target chamber and collimator box
|
Wednesday 7 April
|
Swing
|
|
|
Thursday 8 April
|
Owl
|
|
|
Thursday 8 April
|
Day
|
|
Target chamber open, found that the 4th foil in Optics target blown off
|
Thursday 8 April
|
Swing
|
|
|
Friday 9 April
|
Owl
|
|
|
Friday 9 April
|
Day
|
- To be determined.
- When ready: Install GEMs
|
|
Friday 9 April
|
Swing
|
|
|
Saturday 10 April
|
Owl
|
|
|
Saturday 10 April
|
Day
|
|
|
Saturday 10 April
|
Swing
|
|
|
Sunday 11 April
|
Owl
|
|
|
Sunday 11 April
|
Day
|
|
|
Sunday 11 April
|
Swing
|
|
|
Monday 12 April
|
Owl
|
|
|
Monday 12 April
|
Day
|
|
|
Monday 12 April
|
Swing
|
|
|
Tuesday 13 April
|
Owl
|
|
|
Tuesday 13 April
|
Day
|
|
|
Tuesday 13 April
|
Swing
|
|
Tungsten collimator modified and installed. Target pump down started and initially successful.
|
Wednesday 14 April
|
Owl
|
|
Target pump down.
|
Wednesday 14 April
|
Day
|
- Cancelled -- no shift workers (might need a TO)
- Target pump down and leak checking.
- When ready, begin target cooldown. (Dave Meekins and JP)
|
Done. Vacuum good. Target cold.
|
Wednesday 14 April
|
Swing
|
- Beam restore in Hall A
- Harp Scan - Shifters
- Raster size scan (goal is 3x3mm on empty cell) - Shifters.
- Detector Alignment - Dustin
- Dithering run with Septum On/Off - Rupesh.
|
|
Thursday 15 April
|
Owl
|
- Thick Carbon Integrating Mode Run - Rupesh.
- Thick Carbon Dithering Run - Rupesh + Luis.
- Take Access: Change to counting mode and put sieve in - Ahmed.
|
|
Thursday 15 April
|
Day
|
- Beam Studies -- establishing good beam in Hall A and Compton (Jay and B team)
|
|
Thursday 15 April
|
Swing
|
- Detector Alignment - Dustin.
- Pb Alignment - Bob.
- Take access and put sieve in - Seamus.
- Sieve Alignment - Seamus.
- Take Access to remove sieve (Seamus) + switch to integrating mode (Jon) - Page Guy and Bob.
- Heat load test (run up to 500C) - Bob + Guy.
If possible, depending on heat load test:
- Relative Rate 12C/Pb Runs - Bob / Dustin.
- Start production (Rupesh, Luis, Kent, Krishna)
|
|
Friday 16 April
|
Owl
|
|
|
Friday 16 April
|
Day
|
|
|
Friday 16 April
|
Swing
|
- Production @ 40uA
- Ramp up to 50uA (Guy + Bob)
|
|
Saturday 17 April
|
Owl
|
|
|
Saturday 17 April
|
Day
|
- Production @ 50uA
- Moller Checks + Measurement Starting 9am (Sasha)
|
|
Saturday 17 April
|
Swing
|
- Moller till 7pm (Sasha).
- Compton (Jay Benesch + Megan).
- Production @ 50uA.
|
|
Sunday 18 April
|
Owl
|
|
|
Sunday 18 April
|
Day + Swing
|
- Production @ 50uA.
- Staring 3pm:
- Compton test (Jay Benesch + Megan).
- Page Dustin + Jon + Bob + Sasha.
- Q^2 Measurement (Bob)
- Call Compton Experts
- Access:
- Refill Moller Magnet.
- Check Compton HV.
- Remove S0.
- Go to counting mode (Dustin).
- Compton Stuff.
- Detector Mapping (Jon).
- Detector Alignment (Dustin).
- Q^2 Measurement (Bob).
- Relative Rate Measurement (Bob).
- Access to Return to Integrating Mode.
|
Monday 19 April
|
Owl
|
|
|
Monday 19 April
|
Day
|
|
|
Monday 19 April
|
Swing
|
|
|
Tuesday 20 April
|
Owl
|
|
|
Tuesday 20 April
|
Day
|
- Production
- Beam studies from approx. 11 am to 2 pm
- Hall A Activities:
- -- Compton 1/4wave stepper (Abdurahim)
- -- Check R-HRS Q2 and switch to remote mode (Heidi)
- -- Adjust R-HRS A_T (Dustin)
- -- Take pedestal data (Jon)
- -- Check 4th GEM and possibly install 5th (Alex, Jon)
- -- Test motion of A_T detector R-HRS (Jon)
- -- Possible Compton shielding / HV check (Megan)
- -- Ramp Moller magnet, measure stray fields. (Sasha)
- -- Parasitic work on floor (Yi Qiang)
|
|
Tuesday 20 April
|
Swing
|
- Tune up Compton
- Production
|
|
Wednesday 21 April
|
Owl
|
|
|
Wednesday 21 April
|
Day
|
|
|
Wednesday 21 April
|
Swing
|
|
|
Thursday 22 April
|
Owl
|
|
|
Thursday 22 April
|
Day
|
- Beam studies. Transverse Phase Space Study in Wien. (Reza, Mark, Rupesh)
- At ~2 pm start Moller commissioning
|
|
Thursday 22 April
|
Swing
|
- Finish Moller (10 hours)
- Resume Production
- Don't forget the beam recovery procedure
|
|
Friday 23 April
|
Owl
|
|
|
Friday 23 April
|
Day
|
- Q2 Studies (3 hrs) -- Dustin, Bob
- GEM studies are only parasitic.
|
|
Friday 23 April
|
Swing
|
|
|
Saturday 24 April
|
Owl
|
|
|
Saturday 24 April
|
Day
|
- Production on thick C12
- At about 2 pm switch to 120 Hz, still C12
- Run briefly on C12 at 120 Hz
- Switch to thick Pb target (120 Hz)
|
|
Saturday 24 April
|
Swing
|
- Production on Pb at 120 Hz
|
|
Sunday 25 April
|
Owl
|
|
|
Sunday 25 April
|
Day
|
- Q2 measurements - Bob, Dustin
- Otherwise production
|
done
|
Sunday 25 April
|
Swing
|
|
|
Monday 26 April
|
Owl
|
|
|
Monday 26 April
|
Day
|
|
Wien flip postponed until Tues
|
Monday 26 April
|
Swing
|
|
Tuesday 27 April
|
Owl
|
|
|
Tuesday 27 April
|
Day
|
- Beam Studies
- Wien Flip
- Checks of laser at polarized source (Kent and EGG)
- Adiabatic Damping Study (Yves Roblin)
|
|
Tuesday 27 April
|
Swing
|
Wednesday 28 April
|
Owl
|
|
|
Wednesday 28 April
|
Day
|
|
|
Wednesday 28 April
|
Swing
|
Thursday 29 April
|
Owl
|
|
|
Thursday 29 April
|
Day
|
|
|
Thursday 29 April
|
Swing
|
|