RunPlanDaily

From PREX Wiki
Revision as of 15:05, 18 July 2019 by Tianye (Talk | contribs) (Current Daily Run Plans)

Jump to: navigation, search

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Tuesday, July 16 Owl MOLLER Polarimeter and FFB commissioning
Day production after pass change
Swing change IHWP ('out'), BPM and BCM calibration (Caryn) Done
Wednesday, July 17 Owl Production with 50uA with Aq, BMW and Energy-mode:'RF-off'
Day HallB tuning no beam and frame hunting I
Swing frame hunting II, current scan, Detector and SAM calibration and 70uA production with 12x7.2 raster SAM3 saturation at 70uA?
Wednesday, July 18 Owl IA, PITA scan, 50uA production with with Aq (HallA and C), BMW and FFB off
Day 50 microAmp production, PQB study, FFB test, Moller DAQ, BCM
Swing

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting