RunPlanDaily

From PREX Wiki
Revision as of 10:58, 7 August 2019 by Rakithab (Talk | contribs) (Current Daily Run Plans)

Jump to: navigation, search



PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Tuesday, July 30 Owl low current running beginning at 8am (if approved)
Day Target fix
Swing
  • Tests with no target
  1. collimator centering angles with tune beam
  2. BCM calibrations
  3. BPM calibrations
  4. position feedback study
Wednesday, July 31 Owl production at 70uA
Day
  1. HRS quad repairs
  2. target repairs
  3. Compton work
  4. BCM repair
  1. HRS quad repairs - both operational; nothing really done to right
  2. target repairs - mechanical work done, modifying software for new setpoints
  3. Compton work ongoing
  4. 2nd one working as well as we can tell
Swing
  1. Raster check
  2. Detector alignment (low current)
    • Main detectors
    • AT detectors
  3. BCM test and Current and Pita scans
  4. production at 70uA
Thursday, August 1 Owl production at 70uA
Day production at 70uA
Swing Production running at 70uA
Friday, August 2 Owl Production running at 70uA
Day
  1. Wien flip starting at 8:30am
  2. Compton work in the hall: lens, mode-matching, PPLN tuning
  3. Production 70uA; (IHWP OUT, start slug 26)
raster changed to 4 x 5 mm2 for slug 26
Swing Production running at 70uA
Saturday, August 3 Owl Production running at 70uA
Day
  1. Address issues-- Col. temps, and increased det. widths
  2. Production running at 70uA
changed to Pb9 target
Swing Production running at 70uA
Sunday, August 4 Owl Production running at 70uA
Day Moller starting at 8am
Swing more Moller
Monday, August 5 Owl more Moller
Day
  1. Compton work in Hall
  2. Production running at 70uA
Swing Production running at 70uA
Tuesday, August 6 Owl Production running at 70uA
Day
  1. Production until 10:30 am
  2. Controlled access for Compton work
Swing Production running at 70uA
Wednesday, August 7 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA
Thursday, August 8 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA
Friday, August 9 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting