Difference between revisions of "RunPlanDaily CREX"
From PREX Wiki
(→Current Daily Run Plans) |
(→Current Daily Run Plans) |
||
Line 32: | Line 32: | ||
| Day | | Day | ||
| RF stress test to A/RF fixing | | RF stress test to A/RF fixing | ||
− | | | + | | Burned up 3 raster power supplies (ended test at 4:15pm) |
|- | |- | ||
| Swing | | Swing | ||
− | | | + | | Septum problem (only up to 400 A); collimator centering; polarity check |
− | | | + | | Set HRS tune P for this septum setting |
|- | |- | ||
| rowspan="3" | Friday, December 6 | | rowspan="3" | Friday, December 6 | ||
| Owl | | Owl | ||
− | | | + | | spectrometer setup did not allow target alignment checks |
− | | | + | | Beam gone at 3:40am due to Network issue |
|- | |- | ||
| Day | | Day | ||
− | | | + | | Hall surveyed/controlled access all day; remove diffusor at end? |
− | | | + | | Septum fix complete; network issues being run down; raster sync |
|- | |- | ||
| Swing | | Swing | ||
− | | commissioning | + | | lock up; continue low current commissioning |
− | | | + | | Target hole position |
|- | |- | ||
| rowspan="3" | Saturday, December 7 | | rowspan="3" | Saturday, December 7 |
Revision as of 14:03, 6 December 2019
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | Then 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm) | |
Swing | Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed/controlled access all day; remove diffusor at end? | Septum fix complete; network issues being run down; raster sync | |
Swing | lock up; continue low current commissioning | Target hole position | |
Saturday, December 7 | Owl | commissioning | |
Day | commissioning/ Q2 measurement and Spectrometer rescattering | https://prex.jlab.org/wiki/index.php/RescatteringPlan | |
Swing | commissioning | ||
Sunday, December 8 | Owl | commissioning | |
Day | commissioning | ||
Swing | commissioning | ||
Monday, December 9 | Owl | commissioning | |
Day | diffusor out (if not already); spin dance? | Spin dance if Hall C ready | |
Swing | commissioning/production | ||
Tuesday, December 10 | Owl | commissioning/production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting