Difference between revisions of "RunPlanDaily CREX"

From PREX Wiki
Jump to: navigation, search
(Current Daily Run Plans)
(Current Daily Run Plans)
Line 49: Line 49:
 
| Swing
 
| Swing
 
| lock up; continue low current commissioning
 
| lock up; continue low current commissioning
| Target hole position
+
| Target position alignment checks
 
|-
 
|-
 
| rowspan="3" | Saturday, December 7
 
| rowspan="3" | Saturday, December 7

Revision as of 14:12, 6 December 2019



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Wednesday, December 4 Owl No shift
Day Magnet work...
Swing Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A.
Thursday, December 5 Owl Then 5pass tuning into A.
Day RF stress test to A/RF fixing Burned up 3 raster power supplies (ended test at 4:15pm!)
Swing Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check Set HRS tune P for this septum setting for polarity check
Friday, December 6 Owl spectrometer setup did not allow target alignment checks Beam gone at 3:40am due to Network issue
Day Hall surveyed/controlled access all day; remove diffusor at end? Septum fix complete; network issues being run down; raster sync
Swing lock up; continue low current commissioning Target position alignment checks
Saturday, December 7 Owl commissioning
Day commissioning/ Q2 measurement and Spectrometer rescattering https://prex.jlab.org/wiki/index.php/RescatteringPlan
Swing commissioning
Sunday, December 8 Owl commissioning
Day commissioning
Swing commissioning
Monday, December 9 Owl commissioning
Day diffusor out (if not already); spin dance? Spin dance if Hall C ready
Swing commissioning/production
Tuesday, December 10 Owl commissioning/production
Day production
Swing production

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting