RunPlanDaily CREX
From PREX Wiki
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | Then 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm!) | |
Swing | Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting for polarity check | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed/controlled access all day; remove diffusor at end? | Septum fix; compton work; network issues run down; raster sync investigated | |
Swing | lock up; continue low current commissioning | Target position alignment checks | |
Saturday, December 7 | Owl | start spectrometer commissioning | https://prex.jlab.org/wiki/index.php/CREXRunPlan#Spectrometer_Commissioning |
Day | commissioning/ Q2 measurement and Spectrometer rescattering | https://prex.jlab.org/wiki/index.php/RescatteringPlan | |
Swing | commissioning | ||
Sunday, December 8 | Owl | commissioning | |
Day | commissioning | ||
Swing | commissioning | ||
Monday, December 9 | Owl | commissioning | |
Day | diffusor out (if not already); spin dance? | Spin dance if Hall C ready | |
Swing | commissioning/production | ||
Tuesday, December 10 | Owl | commissioning/production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting