RunPlanDaily CREX
From PREX Wiki
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | Then 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm!) | |
Swing | Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting for polarity check | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed/controlled access all day; remove diffusor at end? | Septum fix; compton work; network issues run down; raster sync investigated | |
Swing | lock up; reverse septum polarity; raster size and hole locations | Left arm NMR probe lock not working; couldn't put any beam on Ca-40 (dump FSDs) | |
Saturday, December 7 | Owl | Tried ion-chamber calibration, but failed; started spec commissioning | First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped |
Day | Jay re-established Yves nominal crex transport; re-check raster size (1.8 x 1.4 now is 2 mm x 2 mm); new hole centers (did not change much); ion-chamber calibrations for Home, C-1%, Ca-40, and Pb#4 (on cold ladder); resumed spec. commissioning | Found out reason for raster optics issues: Moller quads not set correctly after 5-pass backout | |
Swing | Re-did inner-edge septum scan, spot minimization chase (Sangwa, Ciprian) with quartz checkout (Devi); (call Bob) start optics commissioning | We established the preliminary 2 x 2 raster (1.8 x 1.4 MCC), but should be double checked/tweaked before going high current on Calcium | |
Sunday, December 8 | Owl | Continued Optics commissioning | Experts coming in: Bob, Chandan, and Siyu |
Day | commissioning | ||
Swing | commissioning | ||
Monday, December 9 | Owl | commissioning | |
Day | diffusor out (if not already); spin dance? | Spin dance if Hall C ready | |
Swing | commissioning/production | ||
Tuesday, December 10 | Owl | commissioning/production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting