RunPlanDaily CREX

From PREX Wiki
Jump to navigationJump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Comments/Status
Wednesday, December 4 Owl No shift
Day Magnet work...
Swing Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A.
Thursday, December 5 Owl Then 5pass tuning into A.
Day RF stress test to A/RF fixing Burned up 3 raster power supplies (ended test at 4:15pm!)
Swing Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check Set HRS tune P for this septum setting for polarity check
Friday, December 6 Owl spectrometer setup did not allow target alignment checks Beam gone at 3:40am due to Network issue
Day Hall surveyed/controlled access all day; remove diffusor at end? Septum fix; compton work; network issues run down; raster sync investigated
Swing lock up; reverse septum polarity; raster size and hole locations Left arm NMR probe lock not working; couldn't put any beam on Ca-40 (dump FSDs)
Saturday, December 7 Owl Tried ion-chamber calibration, but failed; started spec commissioning First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped
Day Jay re-established Yves nominal crex transport; re-check raster size (1.8 x 1.4 now is 2 mm x 2 mm); new hole centers (did not change much); ion-chamber calibrations for Home, C-1%, Ca-40, and Pb#4 (on cold ladder); resumed spec. commissioning Found out reason for raster optics issues: Moller quads not set correctly after 5-pass backout
Swing Re-did inner-edge septum scan, spot minimization chase (Sangwa, Ciprian) with quartz checkout (Devi); (call Bob) start optics commissioning We established the preliminary 2 x 2 raster (1.8 x 1.4 MCC), but should be double checked/tweaked before going high current on Calcium
Sunday, December 8 Owl Continued Optics commissioning Experts coming in: Bob, Chandan, and Siyu
Day commissioning
Swing commissioning
Monday, December 9 Owl commissioning
Day diffusor out (if not already); spin dance? Spin dance if Hall C ready
Swing commissioning/production
Tuesday, December 10 Owl commissioning/production
Day production
Swing production

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting