Day, Date Shift Tasks (Responsible Party) Comments/Status
Sat Aug 8 Owl waiting for beam..
Day Waiting for beam
Swing Harp scans on 4A and 4B, estimate size at target. If size at target is greater than 100um x100 um, then good to go. Otherwise ask MCC to tune. insert warm C-hole tgt, Request position locks (BPM 4A and 4B) from the white board. Take spot run, analyse and see the C-hole on spectra. Move beam to get C-hole properly. With the proper target center, determine raster currents for 2mmx2mm and 4mmx4mm raster size. When C-hole center and raster current are found, call RC for starting Optics data taking. checked beam spot size from Harp scan - 143um(x)x209um(y). Good enough for our requirement.
Sun Aug 9 Owl
Day Optics commissioning - https://docs.google.com/spreadsheets/d/1SngpqgLLULtcuKD0t9k-A2Cpmxy1jb5bIYnnP8f8zPM/edit#gid=1910123414
Swing
Mon Aug 10 Owl
Day
Swing
Tue Aug 11 Owl
Day
Swing
Wed Aug 12 Owl
Day
Swing
Thr Aug 13 Owl
Day
Swing
Fri Aug 14 Owl
Day
Swing

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting