RunPlanDaily CREX
From PREX Wiki
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, November 25 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Tuesday, November 26 | Owl | No shift | |
Day | Compton work | ||
Swing | Compton work | ||
Wedsday, November 27 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Thursday, November 28 | Owl | No shift | |
Day | Eat Turkey | low current commissioning | |
Swing | Eat more... | ||
Friday, November 29 | Owl | No shift | |
Day | No shift | ||
Swing | |||
Saturday, November 30 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Sunday, December 1 | Owl | No shift | low current commissioning |
Day | Moller Measurement | ||
Swing | Moller Measurement | ||
Monday, December 2 | Owl | No shift | |
Day | Magnet work | ||
Swing | Magnet work | ||
Tuesday, December 3 | Owl | No shift | |
Day | Magnet work | ||
Swing | Magnet work | ||
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | Then 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | ||
Swing | possible low current commissioning / Jack wrap up LQ2/RQ1? | ||
Friday, December 6 | Owl | possible low current commissioning / Jack wrap up LQ2/RQ1? | |
Day | commissioning; diffusor out? | ||
Swing | commissioning | ||
Saturday, December 7 | Owl | commissioning | |
Day | commissioning/ Q2 measurement and Spectrometer rescattering | https://prex.jlab.org/wiki/index.php/RescatteringPlan | |
Swing | commissioning | ||
Sunday, December 8 | Owl | commissioning | |
Day | commissioning | ||
Swing | commissioning | ||
Monday, December 9 | Owl | commissioning | |
Day | diffusor out (if not already); spin dance? | ||
Swing | commissioning/production | ||
Tuesday, December 10 | Owl | commissioning/production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting