RunPlanDaily CREX
From PREX Wiki
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm!) | |
Swing | Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting for polarity check--not conclusive | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed and in controlled access all day; remove diffusor at end? | Septum control software fix; compton e-det work; network issues run down; raster sync problem fixed | |
Swing | lock up hall; reverse septum polarity; raster size and hole locations | Left arm NMR probe lock not working--will have to use Hall probe; couldn't put any beam on Ca-40 due to dump FSDs (and beam optics problem -- MOLLER quads set too high) | |
Saturday, December 7 | Owl | Tried ion-chamber calibration, but failed; started spec commissioning | First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped so need to redo inner edge search |
Day | Jay re-establishes Yves nominal crex beam transport setup; re-check raster size (1.8 x 1.4 now is ~2 mm x 2 mm); new hole centers (did not change much); ion-chamber calibrations done for No target, C-1%, Ca-40, and Pb#4 (on cold ladder); resumed spec. commissioning | Found out reason for raster optics issues: Moller quads not set correctly after 5-pass backout | |
Swing | Re-did inner-edge septum scan, spot minimization chase (Sangwa, Ciprian) with quartz checkout (Devi); (call Bob) start optics commissioning | We established the preliminary 2mm x 2mm (+/-0.1mm) raster (1.8 x 1.4 MCC), but should be double checked/tweaked before going high current on Calcium | |
Sunday, December 8 | Owl | Continued Optics commissioning: dp scans with water-cell measurements most of shift | Experts coming in: Bob, Chandan, and Siyu |
Day | Authorize 150uA; finish optics commissioning; Followup optics studies performed: Q1 scans (-10 to -20%) at +5% septum, nominal tune "P", find best Q1 setting, then scan Q3's to effectively minimumize the FP y widths | th coupling, a lack of the "bow-tie" FP theta v. phi shape, and anomalous structures in the dispersive-x FD distributions | |
Swing | Established CREX tune: "tune P" with +5% septum, -17%/-15% LQ1/RQ1, -5% Q3s. Redo dp optics scan but without w-cell runs, y-target reconstruction | ||
Monday, December 9 | Owl | Finish sieve-in optics plan. Take access for removing sieves; Frame finding and centering for C-1%, Ca-40, and Ca-48; verify quartz alignment; do Q^2 measurements (C1%, Ca-40, Ca-48); quartz rate study for C1%, Ca-40, and Ca-48; Expect very similar rates for all three targets: ~150 - 200k Hz per uA | Experts coming in: Bob, Chandan, and Devi |
Day | high-current commissioning: Compton chicane tuning and ion chamber calibration, setup 150uA to dump; execute Silviu's slow thermal burn-in procedure for Ca-40 (and then Ca-48); beamline instrumentation calibration; go to pre-production width study | ||
Swing | pre-production | ||
Tuesday, December 10 | Owl | pre-production | |
Day | Spin dance? | Spin dance if Hall C ready | |
Swing | production | ||
Wednesday, December 11 | Owl | production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting