RunPlanDaily CREX
From PREX Wiki
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm!) | |
Swing | Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting for polarity check--not conclusive | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed and in controlled access all day; remove diffusor at end? | Septum control software fix; compton e-det work; network issues run down; raster sync problem fixed | |
Swing | lock up hall; reverse septum polarity; raster size and hole locations | Left arm NMR probe lock not working--will have to use Hall probe; couldn't put any beam on Ca-40 due to dump FSDs (and beam optics problem -- MOLLER quads set too high) | |
Saturday, December 7 | Owl | Tried ion-chamber calibration, but failed; started spec commissioning | First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped so need to redo inner edge search |
Day | Jay re-establishes Yves nominal crex beam transport setup; re-check raster size (1.8 x 1.4 now is ~2 mm x 2 mm); new hole centers (did not change much); ion-chamber calibrations done for No target, C-1%, Ca-40, and Pb#4 (on cold ladder); resumed spec. commissioning | Found out reason for raster optics issues: Moller quads not set correctly after 5-pass backout causing wide and short raster settings that evolve to tall and narrow raster at the dump (but 2x2 at the target)... | |
Swing | Re-did inner-edge septum scan, spot minimization chase (Sangwa, Ciprian) with quartz checkout (Devi); (call Bob) start optics commissioning | We established the preliminary 2mm x 2mm (+/-0.1mm) raster (1.8 x 1.4 MCC), but should be double checked/tweaked before going high current on Calcium | |
Sunday, December 8 | Owl | Continued Optics commissioning: dp scans with water-cell measurements most of shift | Experts coming in: Bob, Chandan, and Siyu |
Day | Authorize 150uA; finish optics commissioning; Followup optics studies performed: Q1 scans (-10 to -20%) at +5% septum, nominal tune "P", find best Q1 setting, then scan Q3's to effectively minimumize the FP y widths | The established tune "P" for crex gave large x/th coupling, a lack of the "bow-tie" FP theta v. phi shape, and anomalous structures in the dispersive-x FD distributions; seems to be some quad strength in the septum field that is cancelled out by lowering Q1 | |
Swing | Established CREX tune: "tune P" with +5% septum, -17%/-15% LQ1/RQ1, -5% Q3s. Redo dp optics scan but without w-cell runs, y-target reconstruction | Right dipole tripped OFF at 10:15pm, started ramping back up at 3AM. Aborted sieve-in optics. | |
Monday, December 9 | Owl | Took sieves out and proceeded with frame finding/quartz alignment and rate activities. Bob is working to fix left arm spot. Frame finding and centering for C-1%, Ca-40, and Ca-48; verify quartz alignment; do Q^2 measurements (C-1%, Ca-40, Ca-48); quartz rate study for C-1%, Ca-40, and Ca-48; Expect very similar rates for all three targets: ~150 - 200k Hz per uA | Experts coming in: Bob, Chandan, and Devi |
Day | Finish Frame finding..., put sieves in and finish y recontruction optics plan. go to high-current checkout: setup 150uA to dump no target (can do first Unser calibration here); set SAM and quartz HVs for integration mode; execute Silviu's slow thermal break-in procedure for Ca-40 (and then Ca-48). What other beam instrumentation could be checked-out during thermal break-ins? | When to do Compton chicane tuning? and ion chamber calibration, FFB, and BMW target out--phase advance setup and for production target. This is the preferred order | |
Swing | continued high current commissioning activities | ||
Tuesday, December 10 | Owl | pre-production | |
Day | Spin dance? | Spin dance if Hall C ready | |
Swing | production | ||
Wednesday, December 11 | Owl | production | |
Day | production | ||
Swing | production |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting