Line 243: | Line 243: | ||
| if no spin dance during Day, then continue high-current commissioning | | if no spin dance during Day, then continue high-current commissioning | ||
| When Compton laser system is ready OR we are ready for production data: Preferred order is -Tune through the Compton chicane, ion chamber (re-)calibration, FFB, and BMW target out--phase advance setup and for production target. | | When Compton laser system is ready OR we are ready for production data: Preferred order is -Tune through the Compton chicane, ion chamber (re-)calibration, FFB, and BMW target out--phase advance setup and for production target. | ||
− | ||- | + | | |
+ | |- | ||
| rowspan="3" | Friday, December 13 | | rowspan="3" | Friday, December 13 | ||
| Owl | | Owl |
Revision as of 16:57, 15 December 2019
CREX Main << Run Coordinator Tools << RunPlanDaily_CREX
Copy weekly run plan tables here.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, November 25 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Tuesday, November 26 | Owl | No shift | |
Day | Compton work | ||
Swing | Compton work | ||
Wedsday, November 27 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Thursday, November 28 | Owl | No shift | |
Day | Eat Turkey | low current commissioning | |
Swing | Eat more... | ||
Friday, November 29 | Owl | No shift | |
Day | No shift | ||
Swing | |||
Saturday, November 30 | Owl | No shift | |
Day | No shift | ||
Swing | No shift | ||
Sunday, December 1 | Owl | No shift | low current commissioning |
Day | Moller Measurement | ||
Swing | Moller Measurement | ||
Monday, December 2 | Owl | No shift | |
Day | Magnet work | ||
Swing | Magnet work | ||
Tuesday, December 3 | Owl | No shift | |
Day | Magnet work | ||
Swing | Magnet work | ||
Wednesday, December 4 | Owl | No shift | |
Day | Magnet work... | ||
Swing | Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A. | ||
Thursday, December 5 | Owl | 5pass tuning into A. | |
Day | RF stress test to A/RF fixing | Burned up 3 raster power supplies (ended test at 4:15pm!) | |
Swing | Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check | Set HRS tune P for this septum setting for polarity check--not conclusive | |
Friday, December 6 | Owl | spectrometer setup did not allow target alignment checks | Beam gone at 3:40am due to Network issue |
Day | Hall surveyed and in controlled access all day; remove diffusor at end? | Septum control software fix; compton e-det work; network issues run down; raster sync problem fixed | |
Swing | lock up hall; reverse septum polarity; raster size and hole locations | Left arm NMR probe lock not working--will have to use Hall probe; couldn't put any beam on Ca-40 due to dump FSDs (and beam optics problem -- MOLLER quads set too high) | |
Saturday, December 7 | Owl | Tried ion-chamber calibration, but failed; started spec commissioning | First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped so need to redo inner edge search |
Day | Jay re-establishes Yves nominal crex beam transport setup; re-check raster size (1.8 x 1.4 now is ~2 mm x 2 mm); new hole centers (did not change much); ion-chamber calibrations done for No target, C-1%, Ca-40, and Pb#4 (on cold ladder); resumed spec. commissioning | Found out reason for raster optics issues: Moller quads not set correctly after 5-pass backout causing wide and short raster settings that evolve to tall and narrow raster at the dump (but 2x2 at the target)... | |
Swing | Re-did inner-edge septum scan, spot minimization chase (Sangwa, Ciprian) with quartz checkout (Devi); (call Bob) start optics commissioning | We established the preliminary 2mm x 2mm (+/-0.1mm) raster (1.8 x 1.4 MCC), but should be double checked/tweaked before going high current on Calcium | |
Sunday, December 8 | Owl | Continued Optics commissioning: dp scans with water-cell measurements most of shift | Experts coming in: Bob, Chandan, and Siyu |
Day | Authorize 150uA; finish optics commissioning; Followup optics studies performed: Q1 scans (-10 to -20%) at +5% septum, nominal tune "P", find best Q1 setting, then scan Q3's to effectively minimumize the FP y widths | The established tune "P" for crex gave large x/th coupling, a lack of the "bow-tie" FP theta v. phi shape, and anomalous structures in the dispersive-x FD distributions; seems to be some quad strength in the septum field that is cancelled out by lowering Q1 | |
Swing | Established CREX tune: "tune P" with +5% septum, -17%/-15% LQ1/RQ1, -5% Q3s. Redo dp optics scan but without w-cell runs, y-target reconstruction | Right dipole tripped OFF at 10:15pm, started ramping back up at 3AM. Aborted sieve-in optics. | |
Monday, December 9 | Owl | Took sieves out and proceeded with frame finding/quartz alignment and rate activities. Bob is working to fix left arm spot. R dipole back and stable by 6am, however N Lical went down at 5:30am due to vacuum issue(s) | Experts coming in: Bob, Chandan, and Devi |
Day | SL shift cancelled; TO still required. Hall surveyed and in Controlled Access for opportunistic work | Compton work in the hall; Accelerator down at least until 8 AM next day and may restore beam delivery by 12pm tomorrow | |
Swing | SL shift cancelled; TO still required | ||
Tuesday, December 10 | Owl | SL shift cancelled; TO still required | |
Day | Still investigating vacuum issues in the N. Linac. Spectrometers up and running smooth | Hall in Controlled Access for more Compton e-det and laser work; Hall is ready for beam. Caryn is coordinating a solution to the raster size and FSD lower limit issues | |
Swing | N. Linac problem fixed; waiting for beam | Around 10pm, accel was ready but Ops-controlled valves in the A-line downstream of the wall were not remotely controlable and no remote status update. Problem was investigated, but not properly escalated and continued into Owl | |
Wednesday, December 11 | Owl | No beam all shift; commincation b/t MCC, Hall, and techs was insufficient regarding this valve problem...Shifters could not get any info on the problem or its progress towards resolution... | Continued confusion about what to do with valve problem...Pete Francis get's in at 4am and starts diagnosing |
Day | No beam all shift; trouble shooting remote communication problems on beamline valves and vacuum pressure monitors. | Pete determined it's not a networking issue (other systems on the crate work); it's localized to the status readback and controller cards specific for the valves in the CAMAC crate. Isolated problem to outdated software libraries that crept into system during the RF stress test raster fixes. This problem also affected all downstream of target valves--they were reported as open, but where closed... There is also a problem with 3 cold-cathode probes--not reading back properly (too good and quiet). | |
Swing | When beam is back: Continue spectrometer commissioning with low current (steps 11-13): Frame finding/centering, Q2 and quartz rate study on C-1%, Ca-40, and Ca-48 (Devi or Chandan); verify quartz alignment for Ca-48 (Devi); A_T "box" scans (Devi) | Expect very similar rates for all three targets: ~700k Hz per uA T1 scalar rate | |
Thursday, December 12 | Owl | Finish low current plans, if necessary; then begin a modified high current checkout (note that the ion chamber calibration has already been completed); proceed with steps 1) Basic setup, except with 1% C target and not steering through Compton 2) UNSER calibration (also with 1% C target); then thermal break-in procedure for targets; if these steps are complete continue taking data on Ca-48 (carefully monitoring temps and widths) | What other beam instrumentation could be checked-out during thermal break-ins? |
Day | Spin dance start at 7am if Hall C ready | Notified by Dave that Spin Dance will likely be moved to Friday | |
Swing | if no spin dance during Day, then continue high-current commissioning | When Compton laser system is ready OR we are ready for production data: Preferred order is -Tune through the Compton chicane, ion chamber (re-)calibration, FFB, and BMW target out--phase advance setup and for production target. | |
Friday, December 13 | Owl | high-current commissioning | |
Day | Spin dance cancelled; production when have beam | ||
Swing | high-current commissioning/pre-production | Goal is to get the beamline instrumentation ready for PQB to get a look at regression and widths, etc. (pre-production) | |
Saturday, December 14 | Owl | Production | |
Day | Production, change IHWP, check target pressure with large raster | ||
Swing | Production |