Difference between revisions of "Weekly Meeting Discussion Topics"

From PREX Wiki
Jump to: navigation, search
Line 8: Line 8:
 
|-
 
|-
 
|Scheduling for PQB time at the end of APEX || CG || - || every 6 weeks || 11/27/2018 || -
 
|Scheduling for PQB time at the end of APEX || CG || - || every 6 weeks || 11/27/2018 || -
|-
 
|Beamline checkout || Ye, Bob || - || every 4 weeks || 11/27/2018 || -
 
 
|-
 
|-
 
|Injector setup and feedback || Caryn, Amali || - || every 5 weeks || 12/04/2018 || -
 
|Injector setup and feedback || Caryn, Amali || - || every 5 weeks || 12/04/2018 || -
Line 31: Line 29:
 
|Compton polarimeter || Adam, CG || - || every 4 weeks || 12/18/2018 || -
 
|Compton polarimeter || Adam, CG || - || every 4 weeks || 12/18/2018 || -
 
|-
 
|-
|Cavity Beam Monitors || Ye || - || every 6 weeks || 01/08/2019 || -
+
|Cavity Beam Monitors || Ye || - || every 6 weeks || 11/27/2019 || -
 
|-
 
|-
|Integrating Beam Monitors || CG? || - || - || 01/08/2019 || -
+
|Integrating Beam Monitors || CG || - || - || 01/08/2019 || -
 
|}
 
|}

Revision as of 10:26, 27 November 2018

Back to PREX/CREX_Teleconferences

List of discussion topics

Task Responsible Status Update Last update Link
Scheduling for PQB time at the end of APEX CG - every 6 weeks 11/27/2018 -
Injector setup and feedback Caryn, Amali - every 5 weeks 12/04/2018 -
Beam modulation Victoria, Ye - every 4 weeks 12/04/2018 -
GEM detectors Seamus - every 4 weeks 12/04/2018 -
Ion chamber positions CG - every 6 weeks 12/11/2018 -
Moller polarimeter Eric, Sanghwa - every 4 weeks 12/11/2018 -
Data Acquisition Bob - every 4 weeks 12/11/2018 -
Tracking and optics Chandan, Seamus - every 4 weeks 12/11/2018 -
Integrating detectors Dustin - every 6 weeks 12/18/2018 -
Analyzer Paul - every 4 weeks 12/18/2018 -
Compton polarimeter Adam, CG - every 4 weeks 12/18/2018 -
Cavity Beam Monitors Ye - every 6 weeks 11/27/2019 -
Integrating Beam Monitors CG - - 01/08/2019 -