Difference between revisions of "WAC Notes August 31 2020"

From PREX Wiki
Jump to navigationJump to search
 
(3 intermediate revisions by 2 users not shown)
Line 21: Line 21:
 
'''Daily Meeting [https://bluejeans.com/454783784 BlueJeans]'''
 
'''Daily Meeting [https://bluejeans.com/454783784 BlueJeans]'''
  
=== Production Run List - Slug 208 - IHWP OUT - Flip-RIGHT - Production ===
+
=== Production Run List - Slug 208 - IHWP IN - Flip-RIGHT - Production ===
 +
we started slug 208 (delayed until IHWP flip happens) after slug 206, when slug 207 has finished before, so slug 207 and 208 have the same IHWP state
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8131_000 Run 8131]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8131_000 Run 8131]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8132_000 Run 8132]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8132_000 Run 8132]
Line 30: Line 31:
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8137_000 Run 8137]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8137_000 Run 8137]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8138_000 Run 8138]
 
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8138_000 Run 8138]
 +
* Good - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8142_000 Run 8142]
  
 
== Non-Production Runs and Bad Runs ==
 
== Non-Production Runs and Bad Runs ==
* Junk - [https://prex.jlab.org/analysis/crex/index.php?run=summary/all/run8006_000 Run 8006] -- C-1%
+
* Junk - run 8139-8141 -- trying to restore beam
* Junk - run 8007- 8011
 
  
 
== Issues ==
 
== Issues ==

Latest revision as of 08:21, 1 September 2020

Documentation
HOW TOs for shift crew
Expert Tools
All Expert Contacts



PREX Main << Weekly Analysis Coordinator << WAC Notes CREX << Instructions

WAC Notes August 30 2020 << >> WAC Notes September 1 2020

August 31 2020

Daily Meeting BlueJeans

Production Run List - Slug 208 - IHWP IN - Flip-RIGHT - Production

we started slug 208 (delayed until IHWP flip happens) after slug 206, when slug 207 has finished before, so slug 207 and 208 have the same IHWP state

Non-Production Runs and Bad Runs

  • Junk - run 8139-8141 -- trying to restore beam

Issues

  • beam was quite unstable, we have to go down to 135 uA
  • Hall C failed to change pass due to problem in their target, so we come back to production in a rush.

Updates