Difference between revisions of "CREX Detailed Production plan"
From PREX Wiki
Jump to navigationJump to searchm |
m |
||
Line 2: | Line 2: | ||
== Production Condition Test == | == Production Condition Test == | ||
− | # <font color="blue"> Check the following | + | # <font color="blue"> Check that the following have been performed</font> |
− | #* | + | #* 150uA beam current, through Compton (backgrounds on fingers and Compton photon detector) with no target |
− | #* Establish | + | #* Establish 2x2 (actual) raster. Insert Production Test target (ask Experts which one, probably Ca48). (low current, then ramp up. check collimator water, vary raster size?) |
− | #* Set Detector and SAM voltages (Dustin M) | + | #* Set Detector and SAM voltages as needed with these target rates (Dustin M, Devi A) |
#<font color="blue"> Check Conditions OK</font> | #<font color="blue"> Check Conditions OK</font> | ||
− | #* | + | #*Collimator water |
− | #* | + | #*Thermocouple temperatures |
− | #* | + | #*Radiation monitors |
− | #* | + | #*Ion chamber stability |
− | # <font color="blue"> | + | # <font color="blue"> Set up Locks (these are necessary for main detectors and SAM calibration)</font> |
#*Slow Target Lock on 4A, 4E (jmenu->"slow locks"-> Orbit Locks Expanded View -> HallATGT) | #*Slow Target Lock on 4A, 4E (jmenu->"slow locks"-> Orbit Locks Expanded View -> HallATGT) | ||
− | #* Fast feedback for HallA on (iocse9) | + | #* Fast feedback for HallA on (iocse9) -> If it has been properly commissioned by OPS already, otherwise it can be done later |
#* If beam is going through Compton, HallAComLock should probably be on | #* If beam is going through Compton, HallAComLock should probably be on | ||
− | #* Should HallAMolLock be on? | + | #* Should HallAMolLock be on? -> No! |
#<font color="blue">Parity</font> | #<font color="blue">Parity</font> | ||
#*establish Aq feedback on bcm_an_us | #*establish Aq feedback on bcm_an_us |
Revision as of 13:22, 8 December 2019
PREX version, CREX Calibration Plan
Production Condition Test
- Check that the following have been performed
- 150uA beam current, through Compton (backgrounds on fingers and Compton photon detector) with no target
- Establish 2x2 (actual) raster. Insert Production Test target (ask Experts which one, probably Ca48). (low current, then ramp up. check collimator water, vary raster size?)
- Set Detector and SAM voltages as needed with these target rates (Dustin M, Devi A)
- Check Conditions OK
- Collimator water
- Thermocouple temperatures
- Radiation monitors
- Ion chamber stability
- Set up Locks (these are necessary for main detectors and SAM calibration)
- Slow Target Lock on 4A, 4E (jmenu->"slow locks"-> Orbit Locks Expanded View -> HallATGT)
- Fast feedback for HallA on (iocse9) -> If it has been properly commissioned by OPS already, otherwise it can be done later
- If beam is going through Compton, HallAComLock should probably be on
- Should HallAMolLock be on? -> No!
- Parity
- establish Aq feedback on bcm_an_us
- document pqb conditions
- turn on Helicity Magnets? -1000,1000 for first 2 and -200,200 for second 2?
- Pedestals
- Apply pedestals to japan for SAMs and DETs and compton bpms and cavity bpms. Update bcms and bpms if necessary.
- Take Data
- Take at least 1 hour of data
- Monitor all things above and take screen shots of all parameters above and elog them.
- Run panguin online to examine feedback, Detector widths, Monitor Widths
- Regression slopes check from Tao
- examine simple correlation plots with panguin (are SAMs and DETs normalized in mul tree?)