PREX/CREX Thursday, October 30, 2014 9:30am EDT

From PREX Wiki
Jump to navigationJump to search

Link to the Meeting page PREX/CREX Teleconferences
Last meeting: PREX/CREX Thursday, October 23, 2014 9:30am EDT

The teleconference info is as follows:
       Phone #: +1-888-240-2560 or +1-408-740-7256 and See International Numbers
       Code: 174599135

Agenda

Follow up on outstanding issues. See last week minutes.


Present:
Ciprian, Kent,Caryn, Seamus, KK, Nickie, Rakitha

Minutes


  • Optics/Momentum calibration - Bob, Nickie and Seamus?
    • We have discussed about use of different target during 11-21-2013 meeting
    • Use can Water cell or Gordon-style Gas cell or Hydrocarbon target
    • Nickie has done some initial work with gas target simulation using HAMC
      • Still there may be some work left to be done on setting the simulation either using HAMC of HMS-MC : generator implementation and etc.
    • Our next goal is to make some progress before the collaboration meeting
    • Evaluating optics with gas target include,
      • Differentiate gas and window contributions
      • What do we get at detector plane? elastics or quasi-elastics?
      • Do we get enough gas signal over window signal at detector plane?
      • Can we make the cell long to move windows out of the detector acceptance
      • What are the radiative effects at the gas target?
      • What gas density/pressure to use?
      • How thick the windows needs to be?
      • It would be nice to obtain focal rate distributions from gas target
      • What gas mixture to use? initially planned to have Hydrogen with some inert heavy nucleus (Ne)
    • Once we have some results, it would be nice to have a meeting before the collaboration meeting with Gordon, Nilanga, KK, Kent, Bob, and Nickie
  • Q1 update
    • The current plan is to mount old one of SOS quad into right HRS
    • If they are going to proceed with this, we have to consider about what implication on PREX
      • Can we run PREX without modifications?
      • It appear that due to changes in SOS quad like smaller diameter (25 cm compared with standard 30 cm) there may be about 20% reduction in rate
      • If that is the case we have to consider about how many new PAC days we going to need
      • This is not an urgent matter to discuss in the collaboration meeting but need to keep track the status of the Q1
  • Circulate draft agenda of the meeting that will help to prepare what is expected from various groups before the meeting : Kent
  • KK to talk with Thia about her recent comment regarding the readiness review - KK
    • What we need before the scheduling of experiments? radiation status only? or what else needed?

Misc.

  • Beam parasitic studies needs a to-do list

TO DO Lists

  • We need to have an estimate of how much coulombs used for PREX-I data and an estimate for PREX-II to determine effectively how much more beam time we will use.
  • Have a optic calibration run plan (discussed in 01/16/2014 meeting)
  • It would be nice to have real-time viewer for optics studies in commissioning (disussed in 01/16/2014 meeting)


TO DO Lists link: PREX, CREX