RunPlanDaily
From PREX Wiki
Revision as of 13:01, 13 July 2019 by Chandabindu (Talk | contribs)
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, July 8 | Owl | no beam | |
Day | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Production CW , | |
Swing | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Production CW | |
Tuesday, July 9 | Owl | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Parasitic CW , tuning for higher passes |
Day | Low current, different triggers on C, Pb | Parasitic CW , tuning for higher passes | |
Swing | Low current GEMS,Sieve/switch to integrating (and remove S0?) | Parasitic CW , tuning for higher passes | |
Wednesday, July 10 | Owl | Detector alignment and low current counting mode | CW low current |
Day | High current Isotopic Lead,set HVs, BMW, current scan, PITA/IA scan Detailed plan | 50uA | |
Swing | Moller commissioning | <2uA | |
Thursday, July 11 | Owl | Finish Moller commissioning, 50uA production runs isotopic lead (BMW, Aq feedabck, FFB on) | Experts are looking at data, FFB was not working |
Day | Hysteresis recovery, machine retuning | Hysteresis recovery done, no beam in the hall. | |
Swing | No beam in the hall | ||
Friday, July 12 | Owl | Planned to 208Pb production and understand noise problem (Cip). Call Paul King+ Cameron for raster sync studies | No beam in the hall |
Day | Expecting beam around noon. After beam comes, try for FFB. If it doesn't work within 30min, go to 208Pb production data and understand noise problem (call Ciprian) | No beam in the hall | |
Swing | Try FFB and 208Pb production. | No beam in the hall | |
Saturday, July 13 | Owl | Ask MCC to tune 65 uA to dump and then ask them to try fast feedback. Give them ~30 min for FFB. Planned to 208Pb production and understand noise problem (call Ciprian). | no beam in the hall |
Day | Continue with owl shift plan. | ||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting