RunPlanDaily
From PREX Wiki
Revision as of 00:35, 13 July 2019 by Chandabindu (talk | contribs)
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, July 8 | Owl | no beam | |
Day | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Production CW , | |
Swing | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Production CW | |
Tuesday, July 9 | Owl | High current Pb, Carbon 1%, BMW, current scan, PITA/IA scan Detailed plan | Parasitic CW , tuning for higher passes |
Day | Low current, different triggers on C, Pb | Parasitic CW , tuning for higher passes | |
Swing | Low current GEMS,Sieve/switch to integrating (and remove S0?) | Parasitic CW , tuning for higher passes | |
Wednesday, July 10 | Owl | Detector alignment and low current counting mode | CW low current |
Day | High current Isotopic Lead,set HVs, BMW, current scan, PITA/IA scan Detailed plan | 50uA | |
Swing | Moller commissioning | <2uA | |
Thursday, July 11 | Owl | Finish Moller commissioning, 50uA production runs isotopic lead (BMW, Aq feedabck, FFB on) | Experts are looking at data, FFB was not working |
Day | Hysteresis recovery, machine retuning | Hysteresis recovery done, no beam in the hall. | |
Swing | No beam in the hall | ||
Friday, July 12 | Owl | Planned to 208Pb production and understand noise problem (Cip). Call Paul King+ Cameron for raster sync studies | No beam in the hall |
Day | Expecting beam around noon. After beam comes, try for FFB. If it doesn't work within 30min, go to 208Pb production data and understand noise problem (call Ciprian) | No beam in the hall | |
Swing | Try FFB and 208Pb production. | No beam in the hall | |
Saturday, July 13 | Owl | Ask MCC to tune 65 uA to dump and then ask them to try fast feedback. Give them ~30 min for FFB. Planned to 208Pb production and understand noise problem (call Ciprian). | |
Day | |||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting